Construction of Revetment23KK0105

Construction of Revetment at Buko Bridge (Abutment A & B), Kinoguitan, Misamis Oriental

Construction of Revetment at Buko Bridge (Abutment A & B), Kinoguitan, Misamis Oriental is a DPWH-tracked public work in KINOGUITAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X. Reported contract value: ₱72,375,000.00. Status: Reported complete (DPWH). Contractor on record: VICENTE T LAO CONST. Figures trace to sumbong.

KINOGUITAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project, Upstream of Dangoan Bridge 1, Medina, Misamis Oriental
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-23-0026225

₱822,712.00 · FY2023

Released to 0000000 Davao del Sur State - College (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

407 projects · ₱34.7B total · 2 flags

4. Implementation

Contract Amount

₱72,375,000.00

Progress

Reported complete (DPWH)

Start Date

April 23, 2023

Target End

February 7, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.