GAA 2022 CSSP22FC0111

CONSTRUCTION OF BYPASS ROAD OF CORY AQUINO BLVD., BRGY. DEL CARMEN, TALISAY, CAMARINES NORTE

CONSTRUCTION OF BYPASS ROAD OF CORY AQUINO BLVD., BRGY. DEL CARMEN, TALISAY, CAMARINES NORTE is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱47,741,145.18. Status: Reported complete (DPWH). Contractor on record: EUS CONST. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱42,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Talisay River Flood Control Structure, Brgy. Binanuan, Talisay, Camarines Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-22-0014169

₱42,786,246.00 · FY2022

Released to Camarines Norte DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

193 projects · ₱9.1B total · 7 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY ALAWIHAO, DAET, CAMAR

Region V, Region V

2024₱144.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP): SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL, BARANGAY MOCONG, BASUD, CAMARINES NORTE (P

Region V, Region V

2023₱144.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MADUNGON RIVER, BARANGAY STA. ANA, SOLSONA, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱141.4M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY ALAWIHAO, DAET, CAMAR

Region V, Region V

2024₱140.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL IN BRGY. SAN ANTONIO, LABO-BRGY. FABRICA (MATOG

Region V, Region V

2024₱140.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP): SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL, BARANGAY MOCONG, BASUD, CAMARINES NORTE (P

Region V, Region V

2023₱140.3M
Past target date (DPWH On-Going)
View all 193 projects →

4. Implementation

Contract Amount

₱47,741,145.18

Progress

Reported complete (DPWH)

Start Date

July 8, 2022

Target End

March 19, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.