Flood Control and Drainage25IA0094

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, CAUCAB TO PALAYAN, ALMERIA, BILIRAN

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, CAUCAB TO PALAYAN, ALMERIA, BILIRAN is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱19,589,985.30. Status: Past target date (DPWH On-Going). Contractor on record: LCTING CONST AND DEVELOPMENT CORP FORMERLY: L C TING CONST. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Inasuyan, Kawayan, Biliran
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-25-0008784

₱5,814,800.00 · FY2025

Released to Home Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

304 projects · ₱17.1B total · 2 flags

4. Implementation

Contract Amount

₱19,589,985.30

Progress

Past target date (DPWH On-Going)

Start Date

March 4, 2025

Target End

September 12, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.