Flood Control and Drainage18HH0049

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BUTUANON RIVER, BRGY. BINALIW - AGSUNGOT, CEBU CITY

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BUTUANON RIVER, BRGY. BINALIW - AGSUNGOT, CEBU CITY is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱41,845,162.82. Status: Reported complete (DPWH). Contractor on record: BNR CONST. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at Butuanon River, Brgy. Binaliw-Agsungot, Cebu City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-18-0032654

₱214,303.00 · FY2018

Released to Minalabac National High De School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

70 projects · ₱4.5B total · 0 flags

Other projects by this contractor

View all 70 projects →

4. Implementation

Contract Amount

₱41,845,162.82

Progress

Reported complete (DPWH)

Start Date

June 18, 2018

Target End

February 28, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.