Roads24DN0113

COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION - CONSTRUCTION OF BARANGAY LUNSAD TO BARANGAY PILA-PILA COASTAL ROAD BINANGONAN, RIZAL (FIRST DISTRICT)

COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION - CONSTRUCTION OF BARANGAY LUNSAD TO BARANGAY PILA-PILA COASTAL ROAD BINANGONAN, RIZAL (FIRST DISTRICT) is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱49,499,996.64. Status: Past target date (DPWH On-Going). Contractor on record: PERSAN CONST INC FORMERLY: PERSAN CONST. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱16,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Malalim na Sapa, Barangay Batingan and Barangay Tatala, Binangonan, Rizal
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-D-24-0014212

₱2,977,141.00 · FY2024

Released to Regional Office - I (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

170 projects · ₱10.0B total · 10 flags

4. Implementation

Contract Amount

₱49,499,996.64

Progress

Past target date (DPWH On-Going)

Start Date

April 29, 2024

Target End

January 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.