Buildings and Facilities25FC0052

COMPLETION OF MULTI-PURPOSE BUILDING IN MALIBAGO ES, BARANGAY MALIBAGO, LABO, CAMARINES NORTE

COMPLETION OF MULTI-PURPOSE BUILDING IN MALIBAGO ES, BARANGAY MALIBAGO, LABO, CAMARINES NORTE is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱1,920,491.85. Status: Past target date (DPWH On-Going). Contractor on record: JAEJR ELECTRICAL CONST. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Follow the peso

3 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2025 · ₱30,000

    Probable match · score 0.86

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROV-25-0015273 · ₱23,806,127

    Possible match · score 0.70

    DBM release source ↗
  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    24% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control / Mitigation at Brgy. Tigbinan, Labo, Camarines Norte (Phase 5)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-25-0015273

₱23,806,127.00 · FY2025

Released to Camarines Norte DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

155 projects · ₱1.1B total · 0 flags

4. Implementation

Contract Amount

₱1,920,491.85

Progress

Past target date (DPWH On-Going)

Start Date

July 24, 2025

Target End

September 21, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.