Roads25HH0121

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD WITH SLOPE PROTECTION STR

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD WITH SLOPE PROTECTION STR is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱96,250,667.01. Status: Past target date (DPWH On-Going). Contractor on record: BNR CONST. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱27,095,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Sapangdaku (Package 3) Cebu City, Cebu
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-25-0008820

₱2,391,464,863.61 · FY2025

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

70 projects · ₱4.5B total · 0 flags

Other projects by this contractor

View all 70 projects →

4. Implementation

Contract Amount

₱96,250,667.01

Progress

Past target date (DPWH On-Going)

Start Date

April 2, 2025

Target End

January 25, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.