CONCRETING OF ROAD INCLUDING DRAINAGE, ALONG NURSERY ROAD TO JCT. ALBERT MORROW BOULEVARD, BARANGAY KATANGAWAN, GENERAL SANTOS CITY, SOUTH COTABATO

CONCRETING OF ROAD INCLUDING DRAINAGE, ALONG NURSERY ROAD TO JCT. ALBERT MORROW BOULEVARD, BARANGAY KATANGAWAN, GENERAL SANTOS CITY, SOUTH COTABATO is a DPWH-tracked public work in South Cotabato 1st DEO, Region XII. Reported contract value: ₱67,550,000.00. Status: Reported complete (DPWH). Contractor on record: LLABAN CONST. Figures trace to dpwh.

South Cotabato 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Silway River, Barangay Simbo, Tupi, South Cotabato
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVIII-21-0015314

₱200,000.00 · FY2021

Released to Sta. Margarita National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

479 projects · ₱8.9B total · 0 flags

4. Implementation

Contract Amount

₱67,550,000.00

Progress

Reported complete (DPWH)

Start Date

April 29, 2021

Target End

March 2, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.