Roads23HN0108

CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION - CONSTRUCTION OF CAUSEWAY, BRGY. TUNGASAN, OLANGO ISLAND, LAPU-LAPU CITY, CEBU

CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION - CONSTRUCTION OF CAUSEWAY, BRGY. TUNGASAN, OLANGO ISLAND, LAPU-LAPU CITY, CEBU is a DPWH-tracked public work in Cebu 6th DEO, Region VII. Reported contract value: ₱14,818,282.69. Status: Reported complete (DPWH). Contractor on record: PHIL ASIA RESOURCES. Figures trace to dpwh.

Cebu 6th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱18,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project, Brgy. Caubian, Olango Island, Lapu-Lapu City, Cebu
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-23-001968

₱52,690,068.00 · FY2023

Released to Eastern Samar State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

25 projects · ₱176.5M total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES-PILIPOG BR.2 (B00002LP) ALONG MACTAN CIRCUMFERENTIAL RD, CORDOVA, CEBU

Cebu 6th DEO, Region VII

2020₱20.9M
Reported complete (DPWH)
No sat.

ROAD WIDENING - SEC. ROADS -MCR- K0027+275 - K0027+675 (MODIFIED TO: OO1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - MACTAN CIRCUMFERENTIAL RD - K0027+275 - K0027+559)

Cebu 6th DEO, Region VII

2021₱17.5M
Reported complete (DPWH)
No sat.

SSP: SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - IMPROVEMENT OF ROAD WITH DRAINAGE SYSTEM AT S. OSMENA ST., LAPU-LAPU CITY, CEBU

Cebu 6th DEO, Region VII

2025₱14.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, SIKATUNA ST., LEADING TO PARI-AN HERITAGE SHRINE, CASA GORORDO, METROPOLITAN CATHEDRAL, BRGY. ZAPATERA, CEBU CITY

Cebu City DEO, Region VII

2018₱12.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, P. ATILLO TO M. GOCHAN STREET, LEADING TO UPTOWN AREA OF CEBU CITY, LABANGON AND BANAWA, CEBU CITY

Cebu City DEO, Region VII

2019₱12.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, SANCIANGKO STREET LEADING TO PARI-AN HERITAGE SHRINE, CASA GORORDO METROPOLITAN CATHEDRAL, TABO-AN PUBLIC MARKET, BRGY. KAMAGAYAN (POB.), CEBU CITY

Cebu City DEO, Region VII

2018₱11.9M
Reported complete (DPWH)
View all 25 projects →

4. Implementation

Contract Amount

₱14,818,282.69

Progress

Reported complete (DPWH)

Start Date

May 11, 2023

Target End

October 7, 2023