Flood Control and Drainage20EA0017

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF BAMBAN FLOOD CONTROL BOAC, MARINDUQUE

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF BAMBAN FLOOD CONTROL BOAC, MARINDUQUE is a DPWH-tracked public work in Marinduque DEO, Region IV-B. Reported contract value: ₱48,627,023.12. Status: Reported complete (DPWH). Contractor on record: E M CUERPO INC. Figures trace to dpwh.

Marinduque DEO, Region IV-B
Region: Region IV-B

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2020 · ₱49,620

    Probable match · score 0.90

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-B-20-0022614 · ₱6,875,373 · release to the district office, not itemized per project

    Possible match · score 0.62

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 20EA0017 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2014-07-29 → 2014-07-29

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Marinduque

Based on the coordinates published with the DPWH record and NOAH file Marinduque.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF BAMBAN FLOOD CONTROL BOAC, MARINDUQUE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱49,620,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bamban Flood Control Boac, Marinduque
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-20-0022614

₱6,875,373.00 · FY2020

Released to National Nutrition Council (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

86 projects · ₱10.2B total · 0 flags

Other projects by this contractor

REHABILITATION OF DIKE SYSTEM ALONG SOLSONA RIVER (BREACHED AND ERODED DIKE, LEFT AND RIGHT BANK), LAOAG RIVER BASIN FLOOD CONTROL AND SABO PROJECT

Flood Control Management Cluster, Central Office

2017₱669.3M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAMARINES SUR EXPRESSWAY (PACKAGE 4), SAN FERNANDO-MINALABAC, CAMARINES SUR(2ND LEGISLATIVE DISTRICT)

Region V, Region V

2022₱482.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES - CONSTRUCTION (COMPLETION) OF EASTERN VISAYAS MEDICAL CENTER, CANCER CENTER, TACLOBAN CITY

Region VIII, Region VIII

2024₱482.2M
Past target date (DPWH On-Going)
No sat.

RAISING OF FOLDER DIKE INCLUDING SLOPE PROTECTION WORKS (PHASE 4: STA 2+030 TO STA. 2+530, PHASE 5: STA. 5+720 TO STA. 5+200, PHASE 6) BRGY. DAMPALIT, MALABON CITY

Flood Control Management Cluster, Central Office

2017₱284.5M
Past target date (DPWH On-Going)
No sat.

CLUSTER 5: PROJECT 1. BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - NATIONAL BUILDING PROGRAM - CONSTRUCTION OF THREE-STOREY BUILDING, DPWH REGIONAL OFFICE VIII, EQUIPMENT MANAGEMENT DIVISION, PHASE II, BARANGAY PAWING, PALO, LEYTE; PROJECT 2

Region VIII, Region VIII

2023₱277.7M
Past target date (DPWH On-Going)
No sat.

REHABILITATION OF FLOOD CONTROL, PAGSANGA-AN RIVER, ORMOC CITY

Region VIII, Region VIII

2024₱274.3M
Past target date (DPWH On-Going)
View all 86 projects →

4. Implementation

Contract Amount

₱48,627,023.12

Progress

Reported complete (DPWH)

Start Date

February 20, 2020

Target End

August 20, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.