Flood Control and Drainage20MH0019

CONSTRUCTION OF FLOOD CONTROL (ALA RIVER), ESPERANZA, SULTAN KUDARAT ESPERANZA, SULTAN KUDARAT

CONSTRUCTION OF FLOOD CONTROL (ALA RIVER), ESPERANZA, SULTAN KUDARAT ESPERANZA, SULTAN KUDARAT is a DPWH-tracked public work in Sultan Kudarat 2nd DEO, Region XII. Reported contract value: ₱47,505,500.00. Status: Reported complete (DPWH). Contractor on record: MUST ENT. Figures trace to dpwh.

Sultan Kudarat 2nd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control (Ala River), Esperanza, Sultan Kudarat
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-20-0002051

₱2,979,200,000.00 · FY2020

Released to Sultan Kudarat 2nd DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

109 projects · ₱5.0B total · 0 flags

4. Implementation

Contract Amount

₱47,505,500.00

Progress

Reported complete (DPWH)

Start Date

February 26, 2020

Target End

September 12, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.