Flood Control and Drainage20HD0034

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE, CONSTRUCTION OF FLOOD CONTROL ALONG DAYHAGON RIVER PHASE I, MEDELLIN, CEBU

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE, CONSTRUCTION OF FLOOD CONTROL ALONG DAYHAGON RIVER PHASE I, MEDELLIN, CEBU is a DPWH-tracked public work in Cebu 4th DEO, Region VII. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: DUROS DEVELOPMENT CORP. Figures trace to dpwh.

Cebu 4th DEO, Region VII
Region: Region VII

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2020 · ₱50,000

    Probable match · score 0.86

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-BMB-E-20-0005751 · ₱8,048,816 · release to the district office, not itemized per project

    Possible match · score 0.61

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 20HD0034 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-04-04 → 2025-10-05

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · Cebu

Based on the coordinates published with the DPWH record and NOAH file Cebu.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE, CONSTRUCTION OF FLOOD CONTROL ALONG DAYHAGON RIVER PHASE I, MEDELLIN, CEBU

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Dayhagon River Phase I, Medellin, Cebu
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-20-0005751

₱8,048,815.67 · FY2020

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

260 projects · ₱10.6B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/REPAIR /REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, CONCRETING/IMPROVEMENT OF BANTAYAN-MADREDIJOS ROAD SECTION STA. 0+000-STA. 13+032

Region VII, Region VII

2016₱238.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTIPURPOSE BUILDING (LILOAN, MUNICIPAL HALL), LILOAN, CEBU

Region VII, Region VII

2023₱193.0M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM, CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/FACILITIES, CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL), BARANGAY POBL

Region VII, Region VII

2021₱187.2M
Reported complete (DPWH)
No sat.

MFO-1 NATIONAL ROAD NETWORK SERVICES, ASSET PRESERVATION OF NATIONAL ROADS-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS/SLOPE COLLAPSE, AND LANDSLIDE CEBU-BALAMBAN TRANSCENTRAL HIGHWAY, K0036+790-K0036+880; K0031+910-K0031+985

Region VII, Region VII

2017₱162.1M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, CEBU NORTH HAGNAYA WHARF RD - K0098 + 829 - K0099 + 889, K0102 + 000 - K0102 + 680, K0105 + 658 - K0105 + 993

Region VII, Region VII

2025₱158.8M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION-PREVENTIVE MAINTENANCE-SECONDARY ROADS - CALUBIAN JCT-SN ISIDRO-TABANGO-VILLABA-PALOMPON RD K1042+285-K1046+979, VILLABA, LEYTE

Leyte 3rd DEO, Region VIII

2025₱142.8M
Reported complete (100% progress, DPWH status On-Going)
View all 260 projects →

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

February 12, 2020

Target End

December 2, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.