Flood Control and Drainage24C00520

BASIC INFRASTRUCTURE PROGRAM - BIP - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN MIGUEL RIVER-PINAMBARAN SECTION(RIGHT DIKE), BRGY. PINAMBARAN, SAN MIGUEL, BULACAN

BASIC INFRASTRUCTURE PROGRAM - BIP - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN MIGUEL RIVER-PINAMBARAN SECTION(RIGHT DIKE), BRGY. PINAMBARAN, SAN MIGUEL, BULACAN is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱98,999,242.49. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: TOPNOTCH CATALYST BUILDERS INC. Figures trace to dpwh.

Region III, Region III
Region: Region III

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

241 projects · ₱13.6B total · 0 flags

Other projects by this contractor

View all 241 projects →

4. Implementation

Contract Amount

₱98,999,242.49

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

June 17, 2024

Target End

May 12, 2025

5. Audit