Construction of Flood Mitigation Structure24GG0152

Construction of Flood Mitigation Structure along Jalaur River, Brgy. Sohoton to Brgy. Patag, Barotac Nuevo, Iloilo

Construction of Flood Mitigation Structure along Jalaur River, Brgy. Sohoton to Brgy. Patag, Barotac Nuevo, Iloilo is a DPWH-tracked public work in BAROTAC NUEVO (ILOILO), ILOILO, Region VI. Reported contract value: ₱72,274,190.79. Status: Reported complete (DPWH). Contractor on record: EARLY RISER CONST / CMG JR BUILDERS. Figures trace to sumbong.

BAROTAC NUEVO (ILOILO), ILOILO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Jalaur River in Barotac Nuevo, Iloilo
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-24-0014169

₱7,105,450.00 · FY2024

Released to Adiong Memorial State College (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0004974

₱15,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0007676

₱1,767,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0000252

₱315,794.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0007677

₱163,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱72,274,190.79

Progress

Reported complete (DPWH)

Start Date

March 8, 2024

Target End

October 3, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.