Schedule / Date Inconsistencies

Completion before start, implausible duration for cost, or future dates marked complete.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 24GG0152 (₱72.27M) is recorded as completed in 80 days against 209 planned; similar-cost projects take a median of 285 days, putting it in the fastest 2.3%. The contractor may have deployed extra resources or worked overtime to finish ahead of schedule.

Public record entityConstruction of Flood Mitigation Structure along Jalaur River, Brgy. Sohoton to Brgy. Patag, Barotac Nuevo, Iloilo
LocationBAROTAC NUEVO (ILOILO), ILOILO, Region VIContract 24GG0152
Amount₱72,274,190.79 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Flood Mitigation Structure along Jalaur River, Brgy. Sohoton to Brgy. Patag, Barotac Nuevo, Iloilo24GG0152Flood control100%October 3, 2024May 27, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source

Start: March 8, 2024 · Source fetched October 21, 2026

Rule Definition

Compares start, target, and actual dates from Sumbong with contract cost.

Triggering Data & citations

Contract schedule fields are inconsistent or implausible

{
  "issues": [
    "implausibly_short_duration"
  ],
  "startDate": "2024-03-08T00:00:00.000Z",
  "contractId": "24GG0152",
  "actualEndDate": "2024-05-27T00:00:00.000Z",
  "targetEndDate": "2024-10-02T00:00:00.000Z",
  "contractCostPhp": 72274190.79
}

Possible Innocent Explanations

  • Revised dates not yet reflected in Sumbong export
  • Early completion certificate vs planned start typo

Cite this record

Love the Philippines. “Schedule / Date Inconsistencies (C4): Construction of Flood Mitigation Structure along Jalaur River, Brgy. Sohoton to Brgy. Patag, Barotac Nuevo, Iloilo.” Source: sumbong. Data as of October 21, 2026. https://lovethephilippines.com/risk/08708e7d-f5ad-4a5f-a024-ad589bc27f10

The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.

Connected records

Where this project sits

Place (PSGC)
Region VI (Western Visayas)IloiloPototanGuibuangan
Storms whose wind field reached it
Penha 2026Koto 2025Kalmaegi 2025Bualoi 2025
Hazard exposure
Active fault33.5 km to mapped traceGEM Foundation (Philippines catalogue within GEM Global Active Faults)Flood (100-yr rain)outside mapped flood zonesUP NOAH Center / DOST-PAGASA (Project NOAH)Landslideoutside mapped landslide zonesUP NOAH Center / UP NIGS (Project NOAH)Storm surgenot inundated even at SSA4 (>5 m)UP NOAH Center / DOST-PAGASA (Project NOAH)Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.