Bridges24HC0036

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF TALIBON-BIEN UNIDO BRIDGE,

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF TALIBON-BIEN UNIDO BRIDGE, is a DPWH-tracked public work in Bohol 2nd DEO, Region VII. Reported contract value: ₱96,386,000.00. Status: Past target date (DPWH On-Going). Contractor on record: A M ORETA & CO INC 108. Figures trace to dpwh.

Bohol 2nd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of San Francisco Bridge Flood Control Structure, Ubay, Bohol
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bohol 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱96,386,000.00

Progress

Past target date (DPWH On-Going)

Start Date

April 8, 2024

Target End

March 3, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.