Buildings and Facilities20EF0039

CONSTRUCTION OF TRIBAL HALL, BRGY. AMAS, BROOKE'S POINT, PALAWAN

CONSTRUCTION OF TRIBAL HALL, BRGY. AMAS, BROOKE'S POINT, PALAWAN is a DPWH-tracked public work in Palawan 2nd DEO, Region IV-B. Reported contract value: ₱1,960,200.00. Status: Reported complete (DPWH). Contractor on record: PALBIC CONST AND SUPPLY. Figures trace to dpwh.

Palawan 2nd DEO, Region IV-B
Region: Region IV-B

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2020 · ₱44,000

    Probable match · score 0.86

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 20EF0039 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-04-29 → 2019-03-24

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF TRIBAL HALL, BRGY. AMAS, BROOKE'S POINT, PALAWAN

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱44,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tigaplan River Flood Control Structure, Brooke's Point, Palawan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Palawan 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,960,200.00

Progress

Reported complete (DPWH)

Start Date

February 13, 2020

Target End

July 30, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.