Buildings and Facilities20BJ0060

CONSTRUCTION OF MUNICIPAL BUILDING, PHASE 1 KAYAPA, NUEVA VIZCAYA

CONSTRUCTION OF MUNICIPAL BUILDING, PHASE 1 KAYAPA, NUEVA VIZCAYA is a DPWH-tracked public work in Nueva Vizcaya 2nd DEO, Region II. Reported contract value: ₱1,896,840.00. Status: Reported complete (DPWH). Contractor on record: BEGAL DESIGN. Figures trace to dpwh.

Nueva Vizcaya 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱32,458,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Sta. Cruz River Flood Control Structures, Pingkian Section, Pingkian, Kayapa, Nueva Vizcaya
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Nueva Vizcaya 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

21 projects · ₱155.1M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG IBULAO RIVER, STA. 325+444 - STA. 325+685 AND STA. 332+180 - K0332+350, HAPID, LAMUT, IFUGAO

Ifugao 1st DEO, Cordillera Administrative Region

2024₱29.4M
Past target date (DPWH On-Going)
No sat.

REHAB./RECONS'TN. OF RDS. W/ SLIPS, SLOPE COLLAPSE & LANDSLIDE ALONG KIANGAN-TINOC-BUGUIAS RD. K0341+025-K0341+042,K0341+547-K0347+574,K0344+035-K0344+055,K0344+452-K0344+464, K0346+561-K0346+608,K0347+022-K0347+037,K0348+467-K0348+482,K0349+070-K0349+085

Ifugao 1st DEO, Cordillera Administrative Region

2025₱19.7M
Past target date (DPWH On-Going)
No sat.

OFF-CARRIAGEWAY IMPROVEMENT ALONG NUEVA VIZCAYA-IFUGAO-MT. PROVINCE ROAD - K0298 + 450 - K0298 884, K0323+300 K0323+357, K0325+769-K0325+919, K0326+000-K0326+104, K0326+169-K0326+419, K0326+552 -K0326+765, K0326+812-K0326+930, K0326+970-K0327+092, K0327+

Ifugao 1st DEO, Cordillera Administrative Region

2022₱19.2M
Reported complete (DPWH)
No sat.

REPAIR/REHABILITATION ALONG KIANGAN-TINOC-BUGUIAS ROAD, K0328+800 - K0328+950, JULONGAN, KIANGAN, IFUGAO

Ifugao 1st DEO, Cordillera Administrative Region

2022₱19.0M
Reported complete (DPWH)
No sat.

CONCRETING OF SITIO COCOY TO SITIO ABABBA BARANGAY TUKUCAN FMR, BARANGAY TUKUCAN, TINOC, IFUGAO, TINOC, IFUGAO

Ifugao 1st DEO, Cordillera Administrative Region

2021₱11.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ROAD BARANGAY BAGUINGUE, KIANGAN, IFUGAO, BAGUINGE, KIANGAN, IFUGAO

Ifugao 1st DEO, Cordillera Administrative Region

2023₱7.9M
Reported complete (DPWH)
View all 21 projects →

4. Implementation

Contract Amount

₱1,896,840.00

Progress

Reported complete (DPWH)

Start Date

September 13, 2020

Target End

January 10, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.