Construction of Flood Mitigation Structure24KK0059

Construction of River Dike at Minlagas Bridge (Abutment A, Upstream and Downstream), Gingoog City, Misamis Oriental

Construction of River Dike at Minlagas Bridge (Abutment A, Upstream and Downstream), Gingoog City, Misamis Oriental is a DPWH-tracked public work in GINGOOG CITY (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X. Reported contract value: ₱96,500,000.00. Status: Reported complete (DPWH). Contractor on record: RITCHE-NATHALIE DEVELOPMENT CORP FORMERLY: RITCHE-NATHALIE BUILDERS AND GEN MERCHANDISE. Figures trace to sumbong.

GINGOOG CITY (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure ( Downstream of Cabulawan Bridge ) , Lagonglong, Misamis Oriental
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROX-24-0007540

₱1,490,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-24-0007542

₱138,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

48 projects · ₱3.2B total · 5 flags

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Reported complete (DPWH)

Start Date

April 11, 2024

Target End

February 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.