Flood Control and Drainage24KA0144

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY SINANGLANAN, MALAYBALAY CITY, BUKIDNON, BRGY. SINANGLANAN, MALAYBALAY CITY, BUKIDNON

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY SINANGLANAN, MALAYBALAY CITY, BUKIDNON, BRGY. SINANGLANAN, MALAYBALAY CITY, BUKIDNON is a DPWH-tracked public work in Bukidnon 1st DEO, Region X. Reported contract value: ₱120,625,000.00. Status: Past target date (DPWH On-Going). Contractor on record: RITCHE-NATHALIE DEVELOPMENT CORP FORMERLY: RITCHE-NATHALIE BUILDERS AND GEN MERCHANDISE 27501. Figures trace to dpwh.

Bukidnon 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Sinanglanan, Malaybalay City, Bukidnon
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-24-0005803

₱1,716,524.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱120,625,000.00

Progress

Past target date (DPWH On-Going)

Start Date

February 27, 2024

Target End

May 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.