Flood Control and Drainage24K00392

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MAAPAG RIVER (DOWNSTREAM), VALENCIA CITY, BUKIDNON

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MAAPAG RIVER (DOWNSTREAM), VALENCIA CITY, BUKIDNON is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱110,820,177.07. Status: Past target date (DPWH On-Going). Contractor on record: RITCHE-NATHALIE DEVELOPMENT CORP FORMERLY: RITCHE-NATHALIE BUILDERS AND GEN MERCHANDISE. Figures trace to dpwh.

Region X, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

48 projects · ₱3.2B total · 5 flags

4. Implementation

Contract Amount

₱110,820,177.07

Progress

Past target date (DPWH On-Going)

Start Date

August 12, 2024

Target End

August 6, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.