Flood Control and Drainage24CL0040

FLOOD CONTROL WORKS ALONG TAMBAK-BANCAL RIVER (PHASE II), SITIO TAMBAK, BARANGAY PALANGINAN, IBA, ZAMBALES

FLOOD CONTROL WORKS ALONG TAMBAK-BANCAL RIVER (PHASE II), SITIO TAMBAK, BARANGAY PALANGINAN, IBA, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱96,492,773.93. Status: Reported complete (DPWH). Contractor on record: PASCAL CONST. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Follow the peso

2 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2024 · ₱50,000

    Probable match · score 0.86

    DBM GAA source ↗
  2. 2. SARO / NCA release

    Not yet linked

  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · imagery 2023-11-16 → 2025-06-15

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Zambales

Based on the coordinates published with the DPWH record and NOAH file Zambales.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bancal - San Isidro - Mambog River ( Totun Lanum ) Phase 1, Sitio Tambak, ( North Side ) , Barangay Palanginan, Iba, Zambales
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Zambales 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱96,492,773.93

Progress

Reported complete (DPWH)

Start Date

February 19, 2024

Target End

January 13, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.