Bridges25C00022

BRIDGE PROGRAM-WIDENING OF PERMANENT BRIDGES-PLARIDEL-PULILAN BRIDGE (OLD) (BO2092LZ) ALONG MAHARLIKA HIGHWAY (PHASE V), PROVINCE OF BULACAN

BRIDGE PROGRAM-WIDENING OF PERMANENT BRIDGES-PLARIDEL-PULILAN BRIDGE (OLD) (BO2092LZ) ALONG MAHARLIKA HIGHWAY (PHASE V), PROVINCE OF BULACAN is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱47,525,925.55. Status: Past target date (DPWH On-Going). Contractor on record: M3 KONSTRACT CORP FORMERLY:MARGARITA CONST. Figures trace to dpwh.

Region III, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱47,525,925.55

Progress

Past target date (DPWH On-Going)

Start Date

April 14, 2025

Target End

November 9, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.