GAA 2025 OO-225MF0013

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, DALOL RIVER (TELAFAS SECTION - DOWNSTREAM),COLUMBIO, SULTAN KUDARAT

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, DALOL RIVER (TELAFAS SECTION - DOWNSTREAM),COLUMBIO, SULTAN KUDARAT is a DPWH-tracked public work in Sultan Kudarat 1st DEO, Region XII. Reported contract value: ₱96,014,192.35. Status: Past target date (DPWH On-Going). Contractor on record: ABU CONST. Figures trace to dpwh.

Sultan Kudarat 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱96,014,192.35

Progress

Past target date (DPWH On-Going)

Start Date

March 26, 2025

Target End

February 6, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.