Roads18GG0044

RECONSTRUCTION FROM PAVED TO CONCRETE OF TIWI - TALISAY - GUINTAS ROAD, K0274 + 537 - K0275 + 527

RECONSTRUCTION FROM PAVED TO CONCRETE OF TIWI - TALISAY - GUINTAS ROAD, K0274 + 537 - K0275 + 527 is a DPWH-tracked public work in Iloilo 2nd DEO, Region VI. Reported contract value: ₱19,590,249.12. Status: Reported complete (DPWH). Contractor on record: A D PENDON CONST. Figures trace to dpwh.

Iloilo 2nd DEO, Region VI
Region: Region VI

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2018 · ₱20,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROI-18-0033578 · · release to the district office, not itemized per project

    Possible match · score 0.71

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18GG0044 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2012-04-28 → 2022-12-17

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · Road, cost per km (rehabilitation / reconstruction)

₱19,788,130 per km= 0.9x the Region VI median (n=191)

Contract cost ₱19,590,249 ÷ 0.99 km read from the DPWH title (“K0274 + 537 - K0275 + 527”; K-post / station range length). National percentile: 23. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: RECONSTRUCTION FROM PAVED TO CONCRETE OF TIWI - TALISAY - GUINTAS ROAD, K0274 + 537 - K0275 + 527

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Jalaur River Control System along Pototan Dingle Tabugon Road, Pob. Dingle Iloilo
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-18-0033578

₱0.00 · FY2018

Released to Division of Ilocos Sur (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,590,249.12

Progress

Reported complete (DPWH)

Start Date

February 20, 2018

Target End

May 15, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.