Construction of Flood Mitigation Structure21H00029

Construction of Flood Control Structures (Shore Protection), Phase 2 at Lazi, Siquijor

Construction of Flood Control Structures (Shore Protection), Phase 2 at Lazi, Siquijor is a DPWH-tracked public work in SIQUIJOR, Region VII. Reported contract value: ₱86,662,736.91. Status: Reported complete (DPWH). Contractor on record: JASA GD 2000 CONST CORP FORMERLY:JASA BUILDER'S. Figures trace to sumbong.

SIQUIJOR, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure/Shore Protection at Tigbawan and Catamboan, Lazi, Siquijor
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007552

₱70,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0012572

₱50,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0009003

₱70,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVII-21-0000435

₱1,057,476.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013854

₱1,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0008604

₱7,000,000.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

243 projects · ₱9.9B total · 0 flags

Other projects by this contractor

View all 243 projects →

4. Implementation

Contract Amount

₱86,662,736.91

Progress

Reported complete (DPWH)

Start Date

March 1, 2021

Target End

August 18, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.