Flood Control and Drainage17IK0009No coordinates published by DPWH

CONST./EXTENSION OF CALBIGA FLOOD CONTROL STRUCTURE ALONG CALBIGA RIVER, CALBIGA, SAMAR

CONST./EXTENSION OF CALBIGA FLOOD CONTROL STRUCTURE ALONG CALBIGA RIVER, CALBIGA, SAMAR is a DPWH-tracked public work in Samar 2nd DEO, Region VIII. Reported contract value: ₱39,385,114.53. Status: Reported complete (DPWH). Contractor on record: B C CUERPO CONST CORP. Figures trace to dpwh.

Samar 2nd DEO, Region VIII

DPWH did not publish coordinates for this project. Location estimated from the project title (town level only); satellite images may not show the exact site.

Region: Region VIII

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2017 · ₱42,310

    Probable match · score 0.93

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROVIII-17-0025582 · ₱34,565,656 · release to the district office, not itemized per project

    Possible match · score 0.70

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 17IK0009 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONST./EXTENSION OF CALBIGA FLOOD CONTROL STRUCTURE ALONG CALBIGA RIVER, CALBIGA, SAMAR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱42,310,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Extension of Calbiga Flood Control Structure along Calbiga River, Calbiga, Samar
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0025582

₱34,565,656.00 · FY2017

Released to Division of Samar (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

56 projects · ₱3.7B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM, NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTI-PURPOSE/FACILITIES, CONSTRUCTION OF PCOO VISAYAS HUB BUILDING IN BARANGAY SUBANGDAKU, MANDAUE CITY

Region VII, Region VII

2022₱289.5M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS DARAGA, ALBAY DIVERSION ROAD, ALBAY, DARAGA, ALBAY PROVINCE

Region V, Region V

2018₱217.8M
Reported complete (DPWH)
No sat.

WIDENING OF PUERTO PRINCESA SOUTH ROAD FROM TWO(2) TO SIX (6) LANES INCL DRAINAGE STRUCTRES AND OTHER ANCILLARY WORKS K0110+400-K0110+740; K0111+300-K0111+439; K0111+455-K0111+677; K0111+693-K0113+714; K0113+736-K0113+770, NARRA, PALAWAN

Region IV-B, Region IV-B

2018₱144.8M
Reported complete (DPWH)
No sat.

ROAD OPENING/CONCRETING OF CONCEPTION - TAPUL - NAWL - PAGSANGHAN - ANAGASE - STO. NIÑO - MAYDOLOBE - SARAO CANVALS - CARANAS ROAD, PARANAS - MOTIONG SAMAR (PHASE I), SAMAR 2ND LD

Region VIII, Region VIII

2020₱143.9M
Past target date (DPWH On-Going)
No sat.

ROAD OPENING/CONCRETING OF CONCEPTION - TAPUL - NAWL - PAGSANGHAN - ANAGASE - STO. NIÑO - MAYLOBE - SARAO CANVAIS - CARANAS ROAD, PARANAS - MOTIONG, SAMAR (PHASE II), SAMAR 2ND LD

Region VIII, Region VIII

2020₱143.9M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING - BILIRAN CIRCUMFERENTIAL ROAD, K1008+360-K1010+490, K1011+480-K1011+690, K1011+740-K1012+093,K1012+134-K1013+490 (11.4738, 124.4695-11.4788, 124.5436, 11.4862, 124.4503-11.4878, 124.4495, 11.4882, 124.4494-11.4912,..,PROVINCE OF BILIRAN

Biliran DEO, Region VIII

2018₱139.6M
Reported complete (DPWH)
View all 56 projects →

4. Implementation

Contract Amount

₱39,385,114.53

Progress

Reported complete (DPWH)

Start Date

July 18, 2017

Target End

May 13, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.