Flood Control and Drainage25EH0093No coordinates published by DPWH

CONSTRUCTION OF MALAUAY RIVER CONTROL, SAN AGUSTIN, ROMBLON

CONSTRUCTION OF MALAUAY RIVER CONTROL, SAN AGUSTIN, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱0.00. Status: Ongoing (DPWH-reported) (For Procurement (DPWH-reported)). Contractor on record: Contractor not linked in this database. Figures trace to dpwh.

Romblon DEO, Region IV-B

DPWH did not publish coordinates for this project, so it cannot be placed on the map or checked with satellite images.

Region: Region IV-B

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2025 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 25EH0093 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    0% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MALAUAY RIVER CONTROL, SAN AGUSTIN, ROMBLON

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Mabini Flood Control Structure, Barangay Mabini, San Andres, Romblon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Romblon DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱0.00

Progress

For Procurement (DPWH-reported)

Start Date

DPWH didn't publish a start date · Source: DPWH Transparency Portal

Target End

DPWH didn't publish a target completion date · Source: DPWH Transparency Portal

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.