Flood Control and Drainage18MB0020

CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF SILWAY RIVER BANK PROTECTION, STA. 0+000-STA. 0+320, BRGY. LABANGAL & BRGY. DADIANGAS NORTH, GENERAL SANTOS CITY, SOUTH COTABATO

CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF SILWAY RIVER BANK PROTECTION, STA. 0+000-STA. 0+320, BRGY. LABANGAL & BRGY. DADIANGAS NORTH, GENERAL SANTOS CITY, SOUTH COTABATO is a DPWH-tracked public work in South Cotabato 1st DEO, Region XII. Reported contract value: ₱34,299,990.06. Status: Reported complete (DPWH). Contractor on record: J G ORANZA CONST. Figures trace to dpwh.

South Cotabato 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigition Structures and Drainage Systems- Construction of Silway River bank protection, Sta. 0+000-Sta. 0+320, Bgy Labangal & Brgy. Dadiangas North, General Santos City, South Cotabato
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-18-0012182

₱40,000.00 · FY2018

Released to Regional Office - IVA (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

107 projects · ₱4.4B total · 6 flags

4. Implementation

Contract Amount

₱34,299,990.06

Progress

Reported complete (DPWH)

Start Date

March 7, 2018

Target End

September 30, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.