Water Provision and Storage20DN0167

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTORS - RAINWATER COLLETORS IN PUBLIC FACILITIES RIZAL 1ST LEGISLATIVE DISTRICT

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTORS - RAINWATER COLLETORS IN PUBLIC FACILITIES RIZAL 1ST LEGISLATIVE DISTRICT is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱3,964,090.03. Status: Reported complete (DPWH). Contractor on record: FRANZCOR TRADING. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱18,778,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Flood Mitigation Facilities, Taytay River, Taytay, Rizal
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Rizal 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

178 projects · ₱1.9B total · 0 flags

4. Implementation

Contract Amount

₱3,964,090.03

Progress

Reported complete (DPWH)

Start Date

July 30, 2020

Target End

October 27, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.