Flood Control and Drainage24C00513

BASIC INFRASTRUCTURE PROGRAM-BIP-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MADLUM RIVER FSRR, BRGY.TARTARO, SAN MIGUEL, BULACAN(PHASE 5)

BASIC INFRASTRUCTURE PROGRAM-BIP-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MADLUM RIVER FSRR, BRGY.TARTARO, SAN MIGUEL, BULACAN(PHASE 5) is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱98,998,665.62. Status: Reported complete (DPWH). Contractor on record: TOPNOTCH CATALYST BUILDERS INC. Figures trace to dpwh.

Region III, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

241 projects · ₱13.6B total · 65 flags

Other projects by this contractor

View all 241 projects →

4. Implementation

Contract Amount

₱98,998,665.62

Progress

Reported complete (DPWH)

Start Date

June 19, 2024

Target End

May 14, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.