CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING, MAJACOB INTEGRATED SCHOOL,TARANGNAN, SAMAR

CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING, MAJACOB INTEGRATED SCHOOL,TARANGNAN, SAMAR is a DPWH-tracked public work in Samar 1st DEO, Region VIII. Reported contract value: ₱10,116,074.78. Status: Reported complete (DPWH). Contractor on record: ND CARANZO BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Samar 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures, Brgy. Cautod, Sta. Margarita, Samar
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-18-0031970

₱171,788.00 · FY2018

Released to Eastern Samar District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱10,116,074.78

Progress

Reported complete (DPWH)

Start Date

December 18, 2018

Target End

May 16, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.