Buildings and Facilities24HN0157

CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - EVACUATION CENTERS / QUARANTINE FACILITIES / PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENTER IN OLANGO ISLAND (PHASE 2), LAPU-LAPU CITY, CEBU

CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - EVACUATION CENTERS / QUARANTINE FACILITIES / PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENTER IN OLANGO ISLAND (PHASE 2), LAPU-LAPU CITY, CEBU is a DPWH-tracked public work in Cebu 6th DEO, Region VII. Reported contract value: ₱19,760,000.00. Status: Reported complete (DPWH). Contractor on record: GONZALODO ENT. Figures trace to dpwh.

Cebu 6th DEO, Region VII
Region: Region VII

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2024 · ₱20,000 (shared by many projects, not this project's own line)

    Possible match · score 0.80

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 24HN0157 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2023-08-13 → 2025-12-09

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - EVACUATION CENTERS / QUARANTINE FACILITIES / PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENTER IN OLANGO ISLAND (PHASE 2), LAPU-LAPU CITY, CEBU

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Gate at Basak Creek, Lapu - Lapu City, Cebu
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Cebu 6th DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

297 projects · ₱8.5B total · 1 flags

4. Implementation

Contract Amount

₱19,760,000.00

Progress

Reported complete (DPWH)

Start Date

May 20, 2024

Target End

November 9, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.