Roads19PD0020

OFF-CARRIAGEWAY IMPROVEMENT: CONSTRUCTION OF LAYBYS- ON SPECIFIC LOCATION ALONG KENNON ROAD (S00407LZ) KO241+551 TO KO245+828

OFF-CARRIAGEWAY IMPROVEMENT: CONSTRUCTION OF LAYBYS- ON SPECIFIC LOCATION ALONG KENNON ROAD (S00407LZ) KO241+551 TO KO245+828 is a DPWH-tracked public work in Baguio City DEO, Cordillera Administrative Region. Reported contract value: ₱22,050,000.00. Status: Reported complete (DPWH). Contractor on record: A P B CONST. Figures trace to dpwh.

Baguio City DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-A-19-0026253

₱61,610.00 · FY2019

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱22,050,000.00

Progress

Reported complete (DPWH)

Start Date

June 13, 2019

Target End

February 27, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.