GAA 2023 OO-223DO0090

ORGANIZATIONAL OUTCOME 2 - PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG NANGKA RIVER (STA. 0+38

ORGANIZATIONAL OUTCOME 2 - PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG NANGKA RIVER (STA. 0+38 is a DPWH-tracked public work in Rizal 2nd DEO, Region IV-A. Reported contract value: ₱69,480,000.00. Status: Reported complete (DPWH). Contractor on record: PERSAN CONST INC FORMERLY: PERSAN CONST. Figures trace to dpwh.

Rizal 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure Along Puray River, Rodriguez, Rizal
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Rizal 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

170 projects · ₱10.0B total · 10 flags

4. Implementation

Contract Amount

₱69,480,000.00

Progress

Reported complete (DPWH)

Start Date

July 10, 2023

Target End

December 5, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.