Rehabilitation / Major Repair of Flood Control Structure22FO0016

Rehabilitation of San Jose Flood Control Structure, San Jose, Libon, Albay

Rehabilitation of San Jose Flood Control Structure, San Jose, Libon, Albay is a DPWH-tracked public work in LIBON (ALBAY), ALBAY, Region V. Reported contract value: ₱48,997,251.57. Status: Reported complete (DPWH). Contractor on record: MAKAPA CORP. Figures trace to sumbong.

LIBON (ALBAY), ALBAY, Region V
Region: Region V

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2022 · ₱50,000

    Probable match · score 1.00

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-A-22-0002951 · ₱462,581,000

    Possible match · score 0.60

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 22FO0016 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2015-01-08 → 2015-01-08

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Albay

Based on the coordinates published with the DPWH record and NOAH file Albay.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: Rehabilitation of San Jose Flood Control Structure, San Jose, Libon, Albay

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of San Jose Flood Control Structure, San Jose, Libon, Albay
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002951

₱462,581,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROV-22-0005153

₱120,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001740

₱25,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002737

₱6,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002625

₱4,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

123 projects · ₱9.7B total · 5 flags

Other projects by this contractor

No sat.

OO2-PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION/REHABILITATION OF NASISI RIVER FLOOD MITIGATION STRUCTURE(BRGY. CAVASI AND BRGY. TOMOL

Region V, Region V

2022₱192.9M
Past target date (DPWH On-Going)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS:CONST./IMPV'T. OF CADAC-AN RIVER FLOOD CONTROL SYSTEM,JUBAN, SORSOGON

Region V, Region V

2018₱185.2M
Reported complete (DPWH)

Construction/Improvement/Rehabilitation of Cadac-an River Flood Mitigation Structure, Sta. 12+260 - Sta. 12+308 Right Side, Sta. 11+792 - Sta. 12+848 Left Side, Juban, Sorsogon

JUBAN (SORSOGON), SORSOGON, Region V

2022₱174.7M
Reported complete (DPWH)

Construction/Improvement/Rehabilitation of Cadac-an River Flood Mitigation Structure, Sta. 23+752.00 - Sta. 24+575.57 Left Side, Sta. 23+806.50 - Sta. 24+357.50 Right Side, Irosin, Sorsogon

IROSIN (SORSOGON), SORSOGON, Region V

2022₱174.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, NABONTON RIVER, LIGAO CITY, ALBAY

Region V, Region V

2025₱173.6M
Past target date (DPWH On-Going)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS:CONST.OF FLOOD MITIGATION STRUCTURES ALONG SAN AGUSTIN RIVER,LIBON AL

Region V, Region V

2018₱171.0M
Reported complete (DPWH)
View all 123 projects →

4. Implementation

Contract Amount

₱48,997,251.57

Progress

Reported complete (DPWH)

Start Date

February 17, 2022

Target End

November 13, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.