Roads20MD0109

CONCRETING OF ABAGA-GUIOB-LAWAAN ROAD, BRGY. KITACUBONG, POLAYAGAN, BARANGIRAN, ALAMADA, NORTH COTABATO

CONCRETING OF ABAGA-GUIOB-LAWAAN ROAD, BRGY. KITACUBONG, POLAYAGAN, BARANGIRAN, ALAMADA, NORTH COTABATO is a DPWH-tracked public work in Cotabato 1st DEO, Region XII. Reported contract value: ₱18,849,038.09. Status: Reported complete (DPWH). Contractor on record: RDEN CONST. Figures trace to dpwh.

Cotabato 1st DEO, Region XII
Region: Region XII

Follow the peso

2 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2020 · ₱40,000

    Possible match · score 0.83

    DBM GAA source ↗
  2. 2. SARO / NCA release

    Not yet linked

  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-03-16 → 2025-09-06

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Dike along Kabacan River, Brgy. Doles, Magpet, North Cotabato
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Cotabato 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

149 projects · ₱1.1B total · 0 flags

4. Implementation

Contract Amount

₱18,849,038.09

Progress

Reported complete (DPWH)

Start Date

November 18, 2020

Target End

April 18, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.