Flood Control and Drainage21MD0029

LIBUNGAN FLOOD CONTROL PROJECT UPSTREAM OF LIBUNGAN BRIDGE (RIGHT BANK) PHASE VII, POBLACION LIBUNGAN, COTABATO

LIBUNGAN FLOOD CONTROL PROJECT UPSTREAM OF LIBUNGAN BRIDGE (RIGHT BANK) PHASE VII, POBLACION LIBUNGAN, COTABATO is a DPWH-tracked public work in Cotabato 1st DEO, Region XII. Reported contract value: ₱29,105,877.05. Status: Reported complete (DPWH). Contractor on record: RDEN CONST. Figures trace to dpwh.

Cotabato 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Libungan Flood Control Project Upstream of Libungan Bridge (Right Bank) Phase VII, Poblacion Libungan, Cotabato
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Cotabato 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

149 projects · ₱1.1B total · 0 flags

4. Implementation

Contract Amount

₱29,105,877.05

Progress

Reported complete (DPWH)

Start Date

April 7, 2021

Target End

November 25, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.