Flood Control and Drainage16DN0038

REHABILITATION OF BILIBIRAN CREEK, BRGY. BILIBIRAN, BINANGONAN, RIZAL

REHABILITATION OF BILIBIRAN CREEK, BRGY. BILIBIRAN, BINANGONAN, RIZAL is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱2,772,291.00. Status: Reported complete (DPWH). Contractor on record: C F TRINIDAD CONST AND SUPPLIES CORP FOR. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱8,512,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Rehabilitation of Flood Mitigation Facilities of Principal River along Upper Marikina River, Rodriguez River, Brgy. San Rafael, Rodriguez (Montalban), Rizal
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-16-0038824

₱90,245.00 · FY2016

Released to Adiong Memo (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,772,291.00

Progress

Reported complete (DPWH)

Start Date

March 24, 2016

Target End

May 22, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.