Roads25DO0076

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-JCT BATASAN-SN MATEO-RODRIGUEZ BYPASS LINK ROAD, RIZAL

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-JCT BATASAN-SN MATEO-RODRIGUEZ BYPASS LINK ROAD, RIZAL is a DPWH-tracked public work in Rizal 2nd DEO, Region IV-A. Reported contract value: ₱124,413,132.58. Status: Past target date (DPWH On-Going). Contractor on record: PERSAN CONST INC FORMERLY: PERSAN CONST. Figures trace to dpwh.

Rizal 2nd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Mitigation Structure, Barangays San Jose and San Pedro, Morong, Rizal
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Rizal 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

170 projects · ₱10.0B total · 10 flags

4. Implementation

Contract Amount

₱124,413,132.58

Progress

Past target date (DPWH On-Going)

Start Date

March 12, 2025

Target End

March 1, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.