Roads24HB0040

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, VALENCIA, BOHOL STA.0+310.00 - STA.0+480.0

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, VALENCIA, BOHOL STA.0+310.00 - STA.0+480.0 is a DPWH-tracked public work in Bohol 3rd DEO, Region VII. Reported contract value: ₱4,931,903.22. Status: Reported complete (DPWH). Contractor on record: REBER ENT AND CONST. Figures trace to dpwh.

Bohol 3rd DEO, Region VII
Region: Region VII

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2024 · ₱40,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱4,931,903 · REBER ENTERPRISES AND CONSTRUCTION

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-04-23 → 2019-04-23

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, VALENCIA, BOHOL STA.0+310.00 - STA.0+480.0

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control at Alejawan River ( Both Sides ) , Duero and Jagna, Bohol
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bohol 3rd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

24HB0040(ReAd)

₱4,931,903.22 · REBER ENTERPRISES AND CONSTRUCTION

Award / contract ref: 24HB0040(ReAd)

Contractor

36 projects · ₱201.4M total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTI-PURPOSE FACILITIES - REHABILITATION OF DPWH BOHOL 3RD DISTRICT ENGINEERING OFFICE, GUINDULMAN, BOHOL

Bohol 3rd DEO, Region VII

2021₱24.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BATUAN, BOHOL

Bohol 3rd DEO, Region VII

2024₱9.9M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES REHABILITATION (COMPLETION) OF DPWH BOHOL 3RD DEO, GUINDULMAN, BOHOL

Bohol 3rd DEO, Region VII

2022₱9.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - JCT. (TER) ITUM - DUAY - PAYAO ROAD, DUERO LEADING TO CAMP VERDE NATURE PARK, DUERO

Bohol 3rd DEO, Region VII

2024₱9.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION OF ROAD, BRGY. CANDABONG, ANDA, BOHOL STA.0+000 - STA

Bohol 3rd DEO, Region VII

2022₱9.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT)- BAGUMBAYAN-ESTACA (PILAR)-CALUASAN-DA

Bohol 3rd DEO, Region VII

2022₱7.1M
Reported complete (DPWH)
View all 36 projects →

4. Implementation

Contract Amount

₱4,931,903.22

Progress

Reported complete (DPWH)

Start Date

May 6, 2024

Target End

June 21, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.