LOCAL INFRASTRUCTURE PROGRAM-REHABILITATION OF THE PORTION OF THE BALBALEN ROAD AT PUROK 9A TO TAPAW, IRISAN, BAGUIO CITY is a DPWH-tracked public work in Baguio City DEO, Cordillera Administrative Region. Reported contract value: ₱2,957,656.28. Status: Reported complete (DPWH). Contractor on record: BALBALIN ENGINEERING AND CONST. Figures trace to dpwh.

Baguio City DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Follow the peso

2 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2020 · ₱2,000

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    Not yet linked

  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-03-04 → 2025-08-04

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of flood control (box culvert) Phase 2 Purok 1-3, San Antonio Village, Baguio City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Baguio City DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

7 projects · ₱48.0M total · 0 flags

4. Implementation

Contract Amount

₱2,957,656.28

Progress

Reported complete (DPWH)

Start Date

October 25, 2020

Target End

January 2, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.