Buildings and Facilities25GH0094

CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY SALVACION, BALASAN, ILOILO

CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY SALVACION, BALASAN, ILOILO is a DPWH-tracked public work in Iloilo 3rd DEO, Region VI. Reported contract value: ₱2,943,291.29. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: NOE'S BUILDERS. Figures trace to dpwh.

Iloilo 3rd DEO, Region VI
Region: Region VI

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2025 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 25GH0094 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2016-03-17 → 2025-04-01

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY SALVACION, BALASAN, ILOILO

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Barrido, Ajuy, Iloilo
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Iloilo 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,943,291.29

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 24, 2025

Target End

July 6, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.