Buildings and Facilities17LC0190No coordinates published by DPWH

CONSTRUCTION OF 1 STY - 2 CL SCHOOL BUILDING AT SAN JOSE ELEMENTARY SCHOOL, PEÑAPLATA, IGACOS, DAVAO DEL NORTE

CONSTRUCTION OF 1 STY - 2 CL SCHOOL BUILDING AT SAN JOSE ELEMENTARY SCHOOL, PEÑAPLATA, IGACOS, DAVAO DEL NORTE is a DPWH-tracked public work in Davao del Norte DEO, Region XI. Reported contract value: ₱2,880,099.14. Status: Reported complete (DPWH). Contractor on record: LLM UNIFIED BUILDERS. Figures trace to dpwh.

Davao del Norte DEO, Region XI

DPWH did not publish coordinates for this project, so it cannot be placed on the map or checked with satellite images.

Region: Region XI

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2017 · ₱10,000

    Probable match · score 0.86

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-D-17-0025737 · ₱6,325,000 · release to the district office, not itemized per project

    Possible match · score 0.61

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 17LC0190 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF 1 STY - 2 CL SCHOOL BUILDING AT SAN JOSE ELEMENTARY SCHOOL, PEÑAPLATA, IGACOS, DAVAO DEL NORTE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Ising River Upstream, Davao Del Norte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-17-0025737

₱6,325,000.00 · FY2017

Released to Iwahig Prison an Penal Farm (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,880,099.14

Progress

Reported complete (DPWH)

Start Date

December 18, 2017

Target End

April 6, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.