CONSTRUCTION OF ROAD AT BRGY. DAGANG PHASE II, PARACALE, CAMARINES NORTE

CONSTRUCTION OF ROAD AT BRGY. DAGANG PHASE II, PARACALE, CAMARINES NORTE is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱28,517,429.39. Status: Past target date (DPWH On-Going). Contractor on record: WAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control / Mitigation at Brgy. Tigbinan, Labo, Camarines Norte (Phase 5)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Camarines Norte DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱28,517,429.39

Progress

Past target date (DPWH On-Going)

Start Date

April 3, 2025

Target End

October 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.