Roads24II0070

CONCRETING OF ROAD IN BRGY. IMELDA-CAN OMANIO-PIO DEL PILAR (5 KMS), LAPINIG, NORTHER SAMAR

CONCRETING OF ROAD IN BRGY. IMELDA-CAN OMANIO-PIO DEL PILAR (5 KMS), LAPINIG, NORTHER SAMAR is a DPWH-tracked public work in Northern Samar 2nd DEO, Region VIII. Reported contract value: ₱19,779,938.39. Status: Reported complete (DPWH). Contractor on record: CDU CONST. Figures trace to dpwh.

Northern Samar 2nd DEO, Region VIII
Region: Region VIII

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2024 · ₱30,000 (shared by many projects, not this project's own line)

    Possible match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱19,779,938 · CDU CONSTRUCTION

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-01-02 → 2020-01-02

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONCRETING OF ROAD IN BRGY. IMELDA-CAN OMANIO-PIO DEL PILAR (5 KMS), LAPINIG, NORTHER SAMAR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Brgy. Rawis, Laoang, Northern Samar
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Northern Samar 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

24II0070, Concreting of Road

₱19,779,938.39 · CDU CONSTRUCTION

Contractor

Not graded

343 projects · ₱9.6B total · 7 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0861+453 - K0862+355, K0862+380 - K0862+786, K0863+064 - K0863+364, K0863+600 - K0863+685, K0863+685 -

Region VIII, Region VIII

2025₱151.5M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR) - K0734+578 - K0735+526, K0742+826 - K0745+000, SAMAR 1ST LD

Region VIII, Region VIII

2024₱147.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MAROYONDOYON CREEK & KAGLANGKOY CREEK, CATARMAN, NORTHERN SAMAR

Northern Samar 1st DEO, Region VIII

2025₱144.7M
Past target date (DPWH On-Going)
No sat.

VIILP - LOCAL ROADS AND BRIDGES - LOCAL ROADS - ROAD OPENING / CONCRETING OF HINANGUTDAN, STA. RITA TO SAN ROQUE, VILLAREAL, SAMAR (PHASE I)

Region VIII, Region VIII

2020₱136.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM- (KATUPARAN)- ITBAYAT AIRPORT /NIA CIRCUMFERENTIAL ROAD, ITBAYAT, BATANES

Region II, Region II

2022₱106.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - ROAD OPENING/CONCRETING OF HINANGUTDAN - STA. RITA TO SAN ROQUE - VILLAREAL, SAMAR (PHASE III), SAMAR 2ND LD

Region VIII, Region VIII

2021₱99.4M
Reported complete (DPWH)
View all 343 projects →

4. Implementation

Contract Amount

₱19,779,938.39

Progress

Reported complete (DPWH)

Start Date

April 25, 2024

Target End

October 21, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.