Flood Control and Drainage20MH0023

CONSTRUCTION OF RIVER BANK PROTECTION/FLOOD CONTROL AT LIMULAN RIVER (DOWNSTREAM),KALAMANSIG, SULTAN KUDARAT KALAMANSIG, SULTAN KUDARAT

CONSTRUCTION OF RIVER BANK PROTECTION/FLOOD CONTROL AT LIMULAN RIVER (DOWNSTREAM),KALAMANSIG, SULTAN KUDARAT KALAMANSIG, SULTAN KUDARAT is a DPWH-tracked public work in Sultan Kudarat 2nd DEO, Region XII. Reported contract value: ₱28,224,000.00. Status: Reported complete (DPWH). Contractor on record: WOODRIDGE BUILDERS CONST. Figures trace to dpwh.

Sultan Kudarat 2nd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of River Bank Protection / Flood Control at Limulan River (Downstream), Kalamansig, Sultan Kudarat
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Sultan Kudarat 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

66 projects · ₱1.2B total · 0 flags

Other projects by this contractor

View all 66 projects →

4. Implementation

Contract Amount

₱28,224,000.00

Progress

Reported complete (DPWH)

Start Date

March 5, 2020

Target End

November 19, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.