Roads22PK0031

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE: TERTIARY ROADS ALONG LUBUAGAN - BATONG BUHAY - ABRA BOUNDARY ROAD, LUBUAGAN, KA

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE: TERTIARY ROADS ALONG LUBUAGAN - BATONG BUHAY - ABRA BOUNDARY ROAD, LUBUAGAN, KA is a DPWH-tracked public work in Upper Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱1,654,304.18. Status: Reported complete (DPWH). Contractor on record: HKBT CONST. Figures trace to dpwh.

Upper Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Sukiap Flood Control Structure along Chico River Sta. 170+350 - Sta. 170+650 (R.S.),Tanglag, Lubuagan, Kalinga
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Upper Kalinga DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

14 projects · ₱166.7M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF FLOOD CONTROL ALONG CHICO RIV

Upper Kalinga DEO, Cordillera Administrative Region

2024₱29.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY NEW TANGLAG (B/S),

Lower Kalinga DEO, Cordillera Administrative Region

2025₱28.9M
Past target date (DPWH On-Going)
No sat.

(1) RECONSTRUCTION OF THE BAMBOO FOOTBRIDGE AT SAMANG CREEK, SAKKI-ING FOOTBRIDGE AND KALIMANGOWAN FOOTBRIDGE, SITIO PAYAO, BRGY. LOWER UMA, LUBUAGAN, KALINGA(2) RECONSTRUCTION OF SUKLAP SUSPENSION FOOTBRIDGE, SUKLAP, BRGY. TANGLAG, LUBUAGAN KALINGA(3

Cordillera Administrative Region, Cordillera Administrative Region

2020₱19.3M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL PROJECT ALO

Lower Kalinga DEO, Cordillera Administrative Region

2025₱19.3M
Past target date (DPWH On-Going)
No sat.

Construction of Flood Control (liglig GIIPO) along Chico River, Sta. 169 + 650 - Sta. 169 + 950 (RS), Barangay Tanglag, Lubuagan, Kalinga

LUBUAGAN (KALINGA), KALINGA, Cordillera Administrative Region

2023₱16.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP): CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAINWATER COLLECTOR SYSTEM - WATER SUPPLY SYSTEM CONSTRUCTION OF WATER SYSTEM, BARANGAY COMMUNITY WATERWORKS IN OLATA, BARANGAY MABILONG

Upper Kalinga DEO, Cordillera Administrative Region

2022₱14.7M
Reported complete (DPWH)
View all 14 projects →

4. Implementation

Contract Amount

₱1,654,304.18

Progress

Reported complete (DPWH)

Start Date

April 13, 2022

Target End

July 15, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.