Flood Control and Drainage18MA0002

CONSTRUCTION OF RIVER BANK PROTECTION (REVETMENT) AT ESTEROS BRIDGE APPROACHES (UPSTREAM) ALONG COTABATO-ALA-MARBEL ROAD, STA. 0+000-STA. 0+400 COTABATO CITY SIDE (RH 9), COTABATO CITY

CONSTRUCTION OF RIVER BANK PROTECTION (REVETMENT) AT ESTEROS BRIDGE APPROACHES (UPSTREAM) ALONG COTABATO-ALA-MARBEL ROAD, STA. 0+000-STA. 0+400 COTABATO CITY SIDE (RH 9), COTABATO CITY is a DPWH-tracked public work in Cotabato City DEO, Region XII. Reported contract value: ₱46,751,499.61. Status: Reported complete (DPWH). Contractor on record: ABU CONST. Figures trace to dpwh.

Cotabato City DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of River Bank Protection (Revetment) at Esteros Bridge approaches (Upstream) along Cotabato - Ala - Marbel Road Sta. 0+000 - Sta. 0+400 Cotabato City side (R.H. 9), Cotabato City, Maguindanao
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-18-0002575

₱2,613,921.00 · FY2018

Released to Cotabato City DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱46,751,499.61

Progress

Reported complete (DPWH)

Start Date

April 24, 2018

Target End

October 11, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.