Flood Control and Drainage25GK0055

CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT COASTAL BARANGAYS OF TUBURAN - TOMONGTONG AND GAHIT, ENRIQUE B. MAGALONA, NEGROS OCCIDENTAL

CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT COASTAL BARANGAYS OF TUBURAN - TOMONGTONG AND GAHIT, ENRIQUE B. MAGALONA, NEGROS OCCIDENTAL is a DPWH-tracked public work in Negros Occidental 1st DEO, Negros Island Region. Reported contract value: ₱33,766,603.80. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: SILVERGRACES CONST AND CONST SUPPLY. Figures trace to dpwh.

Negros Occidental 1st DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱36,273,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Coastal Barangays of Tuburan-Tomongtong and Gahit, Enrique B. Magalona, Negros Occidental
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Negros Occidental 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

408 projects · ₱4.0B total · 4 flags

4. Implementation

Contract Amount

₱33,766,603.80

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 3, 2025

Target End

October 29, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.